Home Business How Seplat Energy achieved mechanical completion of ANOH Gas Plant
BusinessNews

How Seplat Energy achieved mechanical completion of ANOH Gas Plant

Share
Share

By Chioma Obinagwam

 

A leading Nigerian independent energy company listed on both the Nigerian Exchange Limited and London Stock Exchange, Seplat Energy Plc has announced that the ANOH gas plant installation works reached mechanical completion on 29th December 2023, in line with the revised timetable.

SEPLAT told Confiance News in a statement on Wednesday.

This milestone has been achieved without a single recordable Lost Time Incident (LTI) across 11 million man hours, a testament to the focus of the whole team on safe and secure operations.

The ANOH Gas Processing Company (AGPC), an incorporated joint venture between Seplat Energy and NNPC Gas Infrastructure Company (NGIC) Ltd, is delivering the ANOH gas plant with Phase One processing capacity of 300mmscfd. Upon commencement of operations, the plant will deliver dry gas, condensate, and LPG to customers. It is envisaged that AGPC will sell the gas and LPG domestically, and the condensates to the international market.

The other key steps to first gas, as outlined in the Company’s Interim Results announcement, were the drilling and hook-up of the Upstream wells and completion of essential third-party infrastructure: the OB3 pipeline river crossing and Spur Line connecting OB3 to the gas plant.

Completion of the third well (ASSN-05) was previously announced and the fourth and final well (ASSN-06) planned ahead of first gas has also now been completed by the upstream unit operator, SPDC.

We now look forward to the completion of the necessary plant pre-commissioning activities and essential third-party infrastructure which will enable commissioning of the gas plant and commencement of operations. Our previously communicated guidance for first gas is unchanged.

Roger Brown, Chief Executive Officer of Seplat Energy, said:

“ANOH is an important strategic project for Seplat, it will roughly double our gas production, and we are focused on the path to first gas.

 

“Once completed, ANOH will provide two income streams for Seplat: wet gas sales from OML 53 to the gas plant and dividends from the joint venture ANOH Gas Processing Company, which will operate the plant.

“ANOH’s gas will further reduce Seplat’s and Nigeria’s carbon intensity and increase energy supplied to the Nigerian domestic market.”

 

Please follow and like us:
Share

Leave a comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Start your career with NNPC Limited

Start your career with NNPC Limited
Start your career with NNPC Limited

Member

Don't Miss

Again Ikeja Electric customers experience frustration in recharging energy tokens

By Chioma Obinagwam Customers of Ikeja Electric Distribution Company (DisCo) have been thrown into darkness because they cannot buy tokens and some of...

In four photos, NCC reacts to Executive Order on Critical National Information Infrastructure

By Chioma Obinagwam The infrastructure of the Nigerian Communications Commission (NCC) has now been classified as Critical National Information Infrastructure (CNII). Confiance News...

Related Articles

Again Ikeja Electric customers experience frustration in recharging energy tokens

By Chioma Obinagwam Customers of Ikeja Electric Distribution Company (DisCo) have been...

In four photos, NCC reacts to Executive Order on Critical National Information Infrastructure

By Chioma Obinagwam The infrastructure of the Nigerian Communications Commission (NCC) has...

10 men that changed the face of banking in Nigeria

The Nigerian banking sector has undergone significant transformations over the decades, thanks...

Denmark’s Consul General, FC4S Lagos, others collaborate for enhanced access to dairy products

By Chioma Obinagwam For Nigeria to achieve its nutritional goals, its teaming...

Advertisements